Tohban Report 2013-07-17
From RHESSI Wiki
(Difference between revisions)
(Created page with "{{Infobox Tohban Report| |start_date = 10 July 2013 |end_date = 17 July 2013 |tohban_name = Pascal Saint-Hilaire |tohban_email = shilaire@ssl.berkeley.edu |next_tohban = }} ==...") |
|||
Line 9: | Line 9: | ||
== Solar Activity == | == Solar Activity == | ||
- | 20 C | + | 20 C-class flares, 16 of which observed by RHESSI. |
GOES baseline is ~B4. | GOES baseline is ~B4. | ||
Line 22: | Line 22: | ||
== Detector issues == | == Detector issues == | ||
- | (Amended | + | (Amended 2013/07/24:) |
On the 11th of July there was an arc in detector 7, followed by a increase in noise that can be observed in the monitor rate plots, see link below. | On the 11th of July there was an arc in detector 7, followed by a increase in noise that can be observed in the monitor rate plots, see link below. | ||
Revision as of 18:40, 24 July 2013
Tohban Reports | |
---|---|
Start Date: | 10 July 2013 |
End Date: | 17 July 2013 |
Tohban: | Pascal Saint-Hilaire |
Tohban email: | shilaire@ssl.berkeley.edu |
Next Tohban: | |
List all reports |
Contents |
Solar Activity
20 C-class flares, 16 of which observed by RHESSI. GOES baseline is ~B4.
Memory Management
The SSR empties easily at the end of each set of daily passes.
Data Gaps
No data gaps of note.
Detector issues
(Amended 2013/07/24:) On the 11th of July there was an arc in detector 7, followed by a increase in noise that can be observed in the monitor rate plots, see link below.
Spacecraft Management
Decimation | Normal/Vigorous |
HLAT Decimation | Rear decimation weight 6, no front decimation |
Night time data (fronts) | +/- 4 minutes |
Night time data (rears) | Enabled |
Require extra passes? | No |
Requirement for moving pointer? | No |
Attenuator operation | Normal |
Detector problems? | Detector 7 increased noise |